12/13/2016 - Completed Act 537 Sewage Plan of 2016 delivered to DEP for review

5/4/2017 - DEP approved the Act 537 Sewage Plan Update of 2016 

7/19/2017 - Pennvest Design-only loan of $642,500 approved 

12/5/2017 - Settlement day for Pennvest Design-only loan, funds available at this point for Project design 

8/7/2019 - Pennvest loan/grant application submitted

8/16/2019 - Pennvest notification of loan/grant

3/16/2020 - Lake Carey Sewer Project out to Bid

4/16/2020 - Lake Carey Sewer Project Bids opened

5/7/2020 - Lake Carey Sewer Project Bid Awards

 

 