12/13/2016 - Completed Act 537 Sewage Plan of 2016 delivered to DEP for review
5/4/2017 - DEP approved the Act 537 Sewage Plan Update of 2016
7/19/2017 - Pennvest Design-only loan of $642,500 approved
12/5/2017 - Settlement day for Pennvest Design-only loan, funds available at this point for Project design
8/7/2019 - Pennvest loan/grant application submitted
8/16/2019 - Pennvest notification of loan/grant
3/16/2020 - Lake Carey Sewer Project out to Bid
7/2/2020 - Lake Carey Sewer Project Bid Awards
10/15/2020 - Pennvest Settlement
7/2/2020 - All Construction awards were granted
11/2/2020 - Notice to Proceed was issued